Latrobe Magnesium - turning residual ash into useful magnesium metal


October 2011

Completion of pre-feasibility study

March 2013

Completion of adjustment study

December 2015

Commencement of feasibility study

March 2018

Completion of feasibility study

July 2018

Plant Installation

July 2019

Completion of plant construction and commencement of initial magnesium production of 3,000 tonnes per annum

July 2020

Expansion of initial production capacity to 40,000 tonnes per annum

This page updated: 25/06/2015