Timetable

October 2011

Completion of pre-feasibility study

March 2013

Completion of adjustment study

December 2015

Commencement of feasibility study

September 2017

Completion of feasibility study

September 2017

Plant Installation

September 2018

Completion of plant construction and commencement of initial magnesium production of 3,000 tonnes per annum

September 2019

Expansion of initial production capacity to 40,000 tonnes per annum